SPPC opens qualification for NREP Round 8: Tumair and East Al-Amoah solar PV and Al-Mozeraah wind IPPs, 3,200 MW
Added to site 12 Nov 2026
CountrySaudi Arabia
SectorRenewable Energy
Current stageRequest for qualification (Round 8)
Procurer / clientSaudi Power Procurement Company (SPPC), principal buyer
Value and basisNot disclosed; 3,200 MW in total (1,900 MW solar PV, 1,300 MW wind)
Deadline noteRFQ submission date not published in the reports read; qualification opened 11 November 2026
International eligibilityDevelopers and consortia seeking qualification as IPP bidders (build, own, operate; 25-year PPA with SPPC); detailed criteria in SPPC's RFQ
Evidence checked12 November 2026: Argaam (citing SPA) and Saudi Gulf Projects, both 11 November 2026
Tender referenceNREP Round 8 (no RFQ number published)
Source noticeRead the source notice or report
Project summary
SPPC has opened qualification for NREP Round 8: Tumair solar PV (900 MW, Riyadh), East Al-Amoah solar PV (1,000 MW, Aseer) and Al-Mozeraah wind (1,300 MW, Makkah), 3,200 MW in total.
What to watch
RFQ submission date, qualified developers list and the RFP.
Evidence and access caveats
Press reports (Argaam citing SPA; Saudi Gulf Projects); SPPC notice not read; no deadline or value published.