Nama tenders new 1,400 m³/day Masirah sewage treatment plant
Added to site 1 Nov 2026 New
Project summary
Nama Water Services is tendering the design, supply, construction and commissioning of a new 1,400 cubic metres a day sewage treatment plant on Masirah under T/OWW/T/10060/2026. The official list shows the tender floated on 19 October 2026, with bids due on 30 November 2026. Document purchase closed on 26 October. The RO500 tender fee is distinct from the undisclosed contract value.
What to watch
Check the Nama supplier portal for addenda or revised dates. Confirm the closing hour (the list says 15:00, the general instructions say 2:00 PM) and the 1% bid bond.
Evidence and access caveats
Verified against the official public tender list only. Document purchase has closed, so participation is likely limited to firms that bought documents. Value and duration are unverified. This summary is not the tender documentation.