Verification scope and caveats
Mesaieed–Hamad International Airport jet-fuel pipeline
CountryQatar
SectorOil & Gas
Current stageMonitoring: technical bids reported received
Procurer / clientQatarEnergy
Value and basisContract value not disclosed in the reviewed project report.
Deadline noteTechnical bids were reportedly submitted in September 2026, with commercial proposals expected in October. This is not a verified public bidding deadline.
International eligibilityParticipation in the current competition must be confirmed with QatarEnergy. Its general procurement process requires an approved SAP vendor code; registration does not itself establish prequalification.
Evidence checked2026-10-08 — dated project-stage reporting and official vendor procedures checked; project-specific owner notice not located
Tender referenceApproximately 53 km Jet A-1 pipeline from Mesaieed tank farm to Hamad International Airport
Source noticeRead the source notice or report
Project summary
QatarEnergy's proposed jet-fuel pipeline from Mesaieed to Hamad International Airport has reportedly reached the technical-bid stage. The approximately 53 km project includes pipeline installation, pumping, pigging, metering, electrical infrastructure, leak detection and control systems.
What to watch
Watch for commercial evaluation, an owner-confirmed award and contractor-specific equipment and supply packages. Existing bidders should follow their current invitation instructions.
Evidence and access caveats
MEED reported the procurement stage on 25 September; no current public invitation or awarded contract was verified. This project must not be confused with the separate Ras Laffan–Hamad pipeline commissioned in 2019.