Weekly opportunity briefing

Riyadh airport, grid and water tenders open as Diriyah and Yanbu awards are cancelled

Reporting period: 15–21 November 2026 · Issued Saturday, 21 November

King Salman International Airport has tendered its general consultancy, the Saudi Water Authority, the Ministry of Interior and Saudi Energy have tendered power and water works, and the Sport Ministry has invited bids for two World Cup stadium upgrades. On the contracting side, PIF’s Gulf Coast Development signed SAR412.3m of first agreements at Khafji and listed Saudi firms disclosed Aramco, SPPC and Busaita power awards, while Diriyah Company and SWA cancelled two previously awarded contracts.

Priority deadlines:

22 Nov (World Cup stadium upgrades, Riyadh and Abha, reported); 29 Nov (King Salman International Airport general consultancy, reported); 11 Dec (SWA Al-Hayah pipeline commercial bids, reported); 18 Dec (SWA Jeddah 380kV feeders; enquiries by 8 Dec); 16 Jan 2027 (Ministry of Interior substation, Riyadh; enquiries by 27 Dec). Changed: the Saudi Royal Aviation complex at King Salman International Airport moved from 19 Nov to 31 Jan 2027 (MEED, 20 Nov). No deadline published yet for Saudi Energy’s Al Soudah substations. Still open from earlier issues: 22 Nov (SIO Ahmar and Al-Darham dams, reported); 26 Nov (SIO King Fahd Dam, Bisha); 28 Nov (SWA); 29 Nov (SIO Khamis Mushait–Dalghan line, reported; REGA); 1 Dec (King Salman Stadium early works); 6 Dec (King Salman Airport Zone C1+C2, reported); 9 Dec (Ministry of Transport earth roads); 11 Dec (SWA Ras Muhaisen–Hali Dam); 13 Dec (RGA Road 40 Part 12); 14 Dec (SAR track-design bids, reported); 23 Dec and 6 Jan 2027 (Expo Convention Centre and pavilions); 12 Jan 2027 (RGA Road 40 Parts 1–11); 3 Feb 2027 (Al-Narjis PPP applications). Check buyer addenda and bidder eligibility.

Current Opportunities

Tender issued · reported 13 November
1

King Salman International Airport tenders general consultancy for its Riyadh masterplan

Procurer: King Salman International Airport Development Company (KSIADC)
Scope: Engineering services across design, construction and completion of the masterplan assets, through individual service orders, including peer review of third-party designs
Deadline: 29 November 2026 (time not reported); documents issued 1 November, queries closed 11 November
Value: Not disclosed
International access: Open to multinationals holding an active regional headquarters licence from the Ministry of Investment, per MEED; subcontracting limited to one tier

MEED reported the tender on 13 November; technical and commercial bids are due to be evaluated in December. No official notice, tender reference or value has been seen, so eligibility should be confirmed with the client. The consultancy sits alongside the Terminal 6 main-works tender and the Zone C1+C2 package covered in earlier issues.

Public tender · Etimad, listed 19 November
2

Saudi Water Authority tenders 380kV feeder works for the Jeddah production system

Procurer: Saudi Water Authority (SWA)
Scope: Rehabilitating the main power supply of the Jeddah water production system by modifying the two connection circuits of the 380kV feeders from a Saudi Electricity Company substation
Deadline: 18 December 2026, 09:59 Saudi time; opening 19 December, 10:00; enquiries close 8 December
Reference: Etimad 261139006622; tender 205077
Value: Not disclosed; the SAR1,000 booklet is not the contract value
International access: Unconfirmed; classification not shown on the public listing

The details come from the public Etimad list; the tender page and booklet were not read. Bidders will need to check the required classification and any Saudi Electricity Company approvals for work on the feeder circuits.

Public tender · Etimad, listed 18 November
3

Ministry of Interior tenders a 132/13.8kV substation for its security medical complex in Riyadh

Procurer: Ministry of Interior, General Directorate (Competitions and Contracts Department)
Scope: Construction of a 132/13.8kV main substation, expansion of the source and connection works for the ministry’s security medical complex in Riyadh
Deadline: 16 January 2027, 09:59 Saudi time; opening 17 January, 10:00; enquiries close 27 December
Reference: Etimad 260639007989; tender 61/26/53/1
Value: Not disclosed; the SAR500 booklet is not the contract value
International access: Unconfirmed; activity listed as general construction contracting (public works)

Substation capacity, value and contractor classification are not shown on the public listing. The long bid period, running past the year end, suggests a design-and-build scope that bidders should confirm from the booklet.

Bids invited · reported 20 November
4

Saudi Energy invites bids for two Al Soudah 132/13.8kV substations near Abha

Procurer: Saudi Energy (SE)
Scope: Substations SS-1 and SS-2 at Al Soudah to supply the Soudah Peaks development: 67MVA 132/13.8kV transformers, 132kV GIS, medium-voltage switchgear, automation and telecoms
Deadline: Not reported
Value: Not disclosed
International access: Unconfirmed

Saudi Gulf Projects reported the tender on 20 November. A SAR1.3bn agreement signed in December 2025 with National Grid, a Saudi Energy subsidiary, covers the wider power infrastructure for Soudah. The bid deadline and tender reference should be checked with Saudi Energy.

Bids invited · reported 17 November
5

SWA invites commercial bids for the 15km Al-Hayah water pipeline at Wadi Hali Dam

Procurer: Saudi Water Authority (SWA); Water Transmission Company (WTCO) as main contractor under the proposed structure
Scope: 15km, 60-inch water transmission pipeline, part of the Ras Muhaisen–Al Baha–Makkah system
Deadline: Commercial bids 11 December 2026, reported; expressions of interest were submitted on 5 November
Value: About $40m (SAR150m), MEED estimate
International access: Bidders must form a consortium or joint venture with a selected partner, per MEED

MEED reported the invitation on 17 November. The deadline matches SWA’s Ras Muhaisen–Hali Dam transmission tender on Etimad (261039002409) covered in Issue 12, so the two may be linked; MEED gives no Etimad reference, and bidders should check before treating them as one package.

Tender issued · reported 13 November
6

Sport Ministry tenders upgrades of two World Cup 2034 stadiums in Riyadh and Abha

Procurer: Ministry of Sport
Scope: Upgrades to Prince Faisal bin Fahd Stadium, Riyadh (about 47,000 seats, Round of 32 venue) and King Khalid University Stadium, Abha (over 45,400 seats, Round of 16 venue)
Deadline: 22 November 2026, reported
Value: Not disclosed
International access: Unconfirmed

MEED reported the tender on 13 November, after Issue 12 had closed. The Riyadh stadium was earlier floated as a public-private partnership and is now going ahead as an EPC contract. With the deadline a day after this issue, firms not already bidding should check for any extension.

Deadline extended · reported 20 November
7

Bid deadline for the Saudi Royal Aviation complex at King Salman International Airport moved to 31 January

Procurer: Saudi Royal Aviation (SRA)
Scope: Aviation complex within the airport masterplan, from design development to close-out, with 30 landside and 15 airside buildings
Deadline: 31 January 2027, reported; previously 8 October, then 19 November
Value: About SAR3bn ($817m), MEED estimate
International access: Unconfirmed; airport security clearance requirements apply

This is the second extension since the tender was issued in August. We saw the 20 November MEED report only in summary, so the new date should be confirmed with the client. The extra time gives late entrants a window to form teams.

Awards & Contracting Routes

Agreements signed · reported 18 November
8

PIF’s Gulf Coast Development signs SAR412.3m of first construction and consultancy deals at Khafji

Procurer: Gulf Coast Development (wholly owned by PIF)
Winners: Al Rajhi Building and Construction (works and secondary infrastructure); AECOM (project management and supervision); C-Quest (cost consultancy and quantity surveying)
Value: About SAR412.3m ($110m) for the three agreements combined; split not disclosed
Scope: Design and construction works, earthworks and land grading to start the coastal destination in Khafji Governorate
International access: Prime agreements closed; later packages not yet announced

These are the first construction and consultancy agreements since PIF launched Gulf Coast Development in September, Saudi Gulf Projects reported. The destination covers about 20 sq km with a 10km waterfront near the Kuwait border; phase one, with three neighbourhoods, is targeted for 2030. Residential, hotel and commercial packages are the next opportunities to watch.

Contract signed · exchange disclosure 18 November
9

Gas Arabian Services signs SPPC contract for the Ghazlan 1 gas supply pipelines

Procurer: Saudi Power Procurement Company (SPPC), as principal buyer
Contractor: Gas Arabian Services (GAS), Tadawul-listed
Value: Not disclosed; above 20% of GAS’s 2025 revenue, or more than about SAR288m on Argaam’s revenue figure (estimate)
Scope: Design, engineering, procurement, supply, installation, construction and commissioning tests of the gas supply pipelines
Term: 20 months from signing on 17 November
International access: Prime contract closed; supply and subcontract packages not announced

GAS told Tadawul, via Argaam, that it expects the financial impact in 2027 and 2028. Pipe, valve and installation suppliers should watch for GAS’s procurement for the route and for progress on the Ghazlan 1 plant the pipelines will feed.

Contract signed · exchange disclosure 16 November
10

Al-Jouf Agricultural signs SAR360m 33kV power network contract with ALTEC at Busaita

Procurer: Al-Jouf Agricultural Development Co. (JADCO)
Contractor: ALTEC Limited
Value: SAR360m, excluding VAT
Scope: EPC turnkey 33kV transmission and distribution network with substations, cables, protection and control, telecoms and SCADA, plus two years of operation and maintenance
Term: 13 months’ execution, from signing on 15 November
International access: Prime contract closed

This is a material update to the Issue 12 pipeline item: JADCO had approved SAR398.43m of bids for the project on 12 November, and this is the first signing from that package, under the Liquid Fuel Displacement Program. The remaining packages, including supervision and contract management, are still to be signed.

Contract signed · exchange disclosure 16 November
11

Arabian Pipes signs SAR104m Aramco steel pipe manufacturing and coating contract

Procurer: Saudi Aramco
Contractor: Arabian Pipes Co. (Tadawul-listed)
Value: About SAR104m
Scope: Manufacturing and coating of steel pipes
Term: 12 months from signing on 15 November
International access: Closed supply award

Arabian Pipes expects the financial impact in the second half of 2027, according to its Tadawul statement reported by Argaam. The statement does not name the Aramco project the pipes are for.

Construction contract · reported 17 November
12

UCC Red Sea and Azhar Holding win KUN contract to build Aman Hegra resort in AlUla

Procurer: KUN Investment Holding (80%) with AlUla Development Company, a PIF subsidiary (20%)
Contractor: Joint venture of UCC Red Sea (UCC Holding, Qatar) and Azhar Holding
Value: Not disclosed
Scope: 42 hotel and villa keys and 30 branded residences on an 8 million sq m site at Hegra
Term: About 40 months, according to a Royal Commission for AlUla spokesman
International access: Prime contract closed; subcontract packages not announced

TradeArabia and Saudi Gulf Projects reported the award on 17 November, citing UCC Holding; the signing date was not given. Hegra is Saudi Arabia’s first UNESCO World Heritage Site, so heritage-sensitive fit-out, landscaping and MEP subcontracts are the packages to watch.

Pipeline Watch

Award cancelled · reported 19 November
13

Diriyah Company cancels SAR717m One Hotel main works awarded to Ashoka Buildcon–BEC Arabia

Owner: Diriyah Company
Previous award: February 2026, to a joint venture of Ashoka Buildcon (49%) and BEC Arabia; accepted bid SAR717m ($191m)
Reason: “Internal reasons attributable to the employer”, per the contractor’s filing
Next step: Not known; no re-tender announced
International access: Not applicable until any re-tender

Ashoka Buildcon disclosed the cancellation in a Bombay Stock Exchange filing, Zawya Projects reported on 19 November; Diriyah Company has not commented. Contractors that bid for the One Hotel in Diriyah II should watch for a revised scope or re-tender.

Award cancelled · reported 14 November
14

SWA cancels the Yanbu 300 MLD desalination plant contract awarded to VA Tech Wabag

Owner: Saudi Water Authority (SWA)
Previous award: July 2025, about $272m (SAR1,019m), to VA Tech Wabag; the contract was signed by Wabag but not counter-signed by SWA
Scope: 300 million litres a day seawater reverse osmosis (SWRO) plant at Yanbu
Next step: Not known; SWA informed participants via Etimad, citing internal reasons
International access: Not applicable until any re-tender

This is the second award for the same plant that has not gone ahead: Wabag first announced a win in September 2024 at about $317m. Saudi Gulf Projects reported the cancellation on 14 November, after Issue 12 had closed. Desalination contractors should watch for a re-tender or a change of procurement model.

Best offers submitted · reported 19 November
15

Contractors submit best offers for the Oxagon Highway 55 upgrade

Owner: Not stated in the free summary (Oxagon, NEOM region)
Scope: Upgrade of Highway 55, linking the Red Sea coast with the northwest of the kingdom
Stage: Best and final offers submitted; no award announced
Value: Not disclosed
International access: Bidding closed

MEED reported the best offers on 19 November; only the summary is publicly available, so bidders and values are not known. Subcontractors and suppliers should watch for the award.

Bids submitted · reported 18 November
16

Five bidders submit offers for Enowa’s Oxagon industrial wastewater plant

Owner: Enowa, NEOM’s energy and water utility
Scope: Design-build-operate modular industrial wastewater plant at Oxagon: 35,000 m³/day initially in 5,000 m³/day trains, expandable to 45,000, plus a 1,000 m³/day sanitary package and three years of operation and maintenance
Bidders: Alfanar with Lanke; Alkhorayef; Orascom with Wabag; Safari with Veolia; Wetico with Satco
Value: Up to $165m (SAR619m), MEED estimate
International access: Bidding closed 9 November

MEED reported the bids on 18 November, citing a source. Bid prices, the evaluation timetable and award date are not known. Equipment suppliers and O&M subcontractors should watch for the award.

Before pursuing an opportunity

Check the current invitation, deadline and Saudi local time with the buyer; verify foreign eligibility, registration, classification, prequalification, security, local-content and joint-venture terms. “Reported” deadlines and selections are not confirmation of an unrestricted public tender.

Editorial preparation: 20 November 2026 (Bahrain time); the scan covers 15–21 November. Values described as estimates are not confirmed contract amounts.

GCC Tender News

Independent intelligence covering GCC procurement and projects.

Explore Saudi and other GCC opportunities at gcctendernews.com

Contact us: ananeesh@ventanagulf.com
Advisory contact: +973 3967 1972

Published by Ventana Gulf · Kingdom of Bahrain