GCC Tender News العربيةNewsletter

Reported development

Saudi Arabia · Energy & Water

Saudi Energy receives bids for synchronous condensers at Al Leeth PV and Khushaybi PV 380kV substations, SaudiGulf Projects reports

SaudiGulf Projects reported on 24 November 2026 that Saudi Energy (SE) has received bids to supply and install synchronous condensers at two 380kV bulk supply point (BSP) substations that connect large solar plants to the grid: Al Leeth PV, in the Western Operating Area, and Khushaybi PV, in Qassim Province.

According to the report, both projects are on an engineering, procurement and construction (EPC) basis with completion due within 20 months. Each unit is to provide at least 750 MW·s of inertia and connect to the substation’s existing 380kV gas-insulated switchgear bays.

Not confirmed: the number and names of bidders, prices, the tender reference and the award timing. We have not seen an official notice.

Sources: SaudiGulf Projects, 24 November 2026. Reviewed 25 November 2026.