Oman · Healthcare
Al Nama Hospital construction passes 87% in Al Mudhaibi
Construction of Al Nama Hospital in Al Mudhaibi, North Al Sharqiyah, has exceeded 87%, according to an Oman News Agency report published by Oman Daily on 21 October 2026.
The Ministry of Health project has a total cost of OMR56.05 million and occupies a 428,000-square-metre site. Its planned capacity is 265 beds overall, including 152 inpatient beds, alongside 84 outpatient clinics.
The report quotes ministry projects and engineering-services director Yousuf bin Yaqoub Amboali. Facilities include emergency, imaging, dialysis and intensive-care services, five operating theatres and a helipad.
The update does not give a new completion or opening date. The construction measurement date was not separately specified.
Sources: Oman News Agency via Oman Daily, 21 October 2026; Tamol, 21 October 2026.